Case Studies

All Saints Primary School, Fulham

Location:

Fulham

Contract value:

£400,000

Project brief

This project was for All Saints Church of England Primary School and the works consisted of a complete refurbishment of All Key stage 1 toilets and staff toilets. External concrete repairs, redecorations and fire door replacements. The school was in full occupation throughout the works and we successfully coordinated with staff to ensure the welfare and day to day running was unaffected by our presence.

The project was completed in accordance with the programme and within budget. Due to the success of this project, we have now been asked to look at another school locally as well as a number of other schemes planned by the same client.

In addition to the quality produced, our client was very pleased with the professional and personal service we provided throughout the contract.